Flöha teaching pool - installation of the wooden ceiling

07 June 2021

Another of our projects is taking shape piece by piece: The Flöha teaching pool.

On 2 June 2021, the assembly of the wooden ceiling over the swimming hall in Flöha took place. Within a few hours, the 100 m² ceiling was lifted into place and screwed to the prepared timber. On the same day, the electrical company began laying empty conduits for wiring lights, loudspeakers and other ceiling elements. This was done in millings and drill holes prepared in the factory on the top of the elements.

On the following day, the emergency waterproofing was applied - everything remained dry, the local rain showers that had been announced fortunately did not occur.The wooden elements from LIGNOTREND, which are screwed together and are over 8 m long, form the statically supporting roof ceiling of the bathing hall and are at the same time an acoustic ceiling ready for the surface.

The pictures show some impressions of the assembly of the wooden ceiling and the visualisation of the finished swimming hall.