An important milestone for the transport revolution: The day before yesterday, we celebrated the topping-out ceremony for the new electric bus depot in Treptow together with BVG and all those involved in the project.
Our contribution: A solid foundation for sustainable mobility
We carried out extensive soil improvement measures across an area of 4.4 hectares to lay the foundations for future operations:
- 9,000 full displacement piles made of in-situ concrete (Ø 36 cm)
- Geogrid-reinforced base course
- Complete property and structural design (LPH 1-6)
The result:
A modern location where the BVG's electric bus fleet is charged, serviced, and prepared for daily use.
Thank you to the BVG and all project partners for their trusting cooperation.